11th Avenue Improvements

Print
Press Enter to show all options, press Tab go to next option

11th Ave S

Project Description
The sanitary sewer infrastructure in 11th Avenue South and Park Street is mostly 6 inch clay. The pipes are deteriorated and filled with tree roots, which is allowing inflow and infiltration of groundwater into the sanitary sewer. This project, when completed, will upgrade the existing water and sewer lines to provide better service to the customers in the area.

Length & Limits
Approximately 1,200 linear feet of 8 inch diameter sanitary sewer line and1,800 linear feet of 6 inch diameter water line within the proximity of 11th Avenue South from West Main Street to Park Street; Park Street from 11th Avenue South to the existing alley.

Project Contact
Patricia Proctor, PE – Utilities Project Manager patricia.proctor@franklintn.gov
(615) 791-3218

Project Documents
11th Avenue - Exhibit 1
11th Avenue - Exhibit 2